Davis Adv. Sh. No. 26
S.E. 2d

THE STATE OF SOUTH CAROLINA

In The Supreme Court

Brasington Tile Company, Inc.,

Appellant,

v.

Harold G. Worley,

Respondent.

South Carolina National Bank,

Fabmaster, Inc., and Space

Metal Fabricators, Inc.,

Defendants.

Appeal From Horry County

John M. Leiter, Special Referee

Opinion No. 24683

Heard February 18, 1997 - Filed September 2, 1997

AFFIRMED

R. Dean Welch, of Welch Law Firm, P.A., of Surfside Beach, for

Appellant.

Timothy E. Madden and David H. Wilkins, both of Wilkins & Madden,

of Greenville, for Respondent.

TOAL, A.J.: In this action to recover on a mechanic's lien, Appellant Brasington

Tile Company ("Contractor") appeals the special referee's determination that Respondent

Worley ("Owner") was the prevailing party in the litigation and was, therefore, entitled

to attorneys' fees. We affirm.

FACTUAL/PROCEDURAL BACKGROUND

Owner is the proprietor of the O.D. Cafe, a restaurant and bar in North Myrtle

p21


BRASINGTON TILE CO., INC. v. HAROLD G. WORLEY, et al.

Beach. When the restaurant needed renovations, Owner hired Contractor to perform some

of the necessary work. In order to speed up the work, Owner allowed Contractor's

employees to stay at a motel owned by Owner, and Owner gave Contractor a substantial

discount on the room rates.

When Contractor's participation in the renovation project ceased, Owner and

Contractor disagreed about the amount Owner owed Contractor. On July 18, 1991,

Contractor filed a mechanic's lien against the property in the amount of $34,200.46.

Three months later, on October 18, 1991, Contractor sued Owner to foreclose the

mechanic's lien.1 Owner's answer contained a counterclaim as well as a claim for setoffs

and credits. Owner requested that any amounts he owed Contractor be offset by the

amount Contractor owed him for the motel room charges for Contractor's employees.

A special referee heard the action and ruled Contractor was entitled to recover

under his mechanic's lien. Initially, the referee awarded Contractor $14,846.81, having

determined Contractor was entitled to $18,376.062 less $3,529.25 in offsets. Of the offset

amount, $2,595.50 represented the value of the motel accommodations. The special

referee also awarded Contractor attorneys' fees and costs of $14,846.81 plus prejudgment

interest at 8.75%.

Owner filed a motion under Rule 59(e), SCRCP, asking the special referee to

reconsider, among other things, the determination that Contractor was entitled to attorneys'

fees and costs. On February 15, 1996, the special referee modified his original order,

finding Owner the prevailing party as defined in S.C. Code Ann. § 29-5-10 (1991) and

awarding Owner attorneys' fees and costs in the amount of $14,846.8l.3

Contractor appeals on three grounds:

1. There was not sufficient mutuality of interests for the claim regarding motel

accommodations to be treated as a setoff;


1 Other interested parties were named and appeared in the lawsuits, but none of the

claims by or against those parties are relevant to the resolution of this appeal.

2 The original order misstated this amount as $16,216.06. The order issued

pursuant to Owner's Rule 59(e) motion explained that the $16,216.06 figure had simply

been a scrivener's error and that $18,376.06 was the correct amount.

3 Contractor's appeal concerns Owner's entitlement to attorneys' fees, not the

amount of the fee awarded.

p22


BRASINGTON TILE CO., INC. v. HAROLD G. WORLEY, et al.

2. In determining the prevailing party in this action, the special referee should have

regarded the verdict as the amount to which Contractor was entitled before the offsets were

considered; and

3. In determining the prevailing party under section 29-5-10, the special referee

should have considered Owner's counterclaim a "negative" offer of settlement.

LAW/ANALYSIS

A. PROPRIETY OF SETOFF

Contractor first argues that Owner's claim for the cost of motel accommodations

should not be considered a setoff or a counterclaim and should not, therefore, have been

brought in this action. We disagree.

The Record does not reflect that Contractor ever raised to the special referee the

propriety of the setoff itself. In its Reply to Owner's original Answer, Contractor simply

stated that the allegations relating to the setoff "require[d] no response." The Record

contains no objection by Contractor to Owner's introducing evidence concerning the value

of the motel accommodations. If Contractor considered the motel accommodations an

improper subject for setoff, it should have raised the issue to the special referee. As it

failed to do so, the issue is not properly before this Court. See, e.g., Smith v. Phillips,

318 S.C. 453, 458 S.E.2d 427 (1995)(appellate court may not reach issue not raised to or

ruled upon by trial court).

On the merits of this issue, we find there is sufficient mutuality for the claim

relating to motel accommodations to be asserted as a setoff. Courts "generally do not,

with respect to a setoff, require the same strict degree of mutuality as is required in a

counterclaim." Kirkland, Inc. v. Providence Washington Ins. Co., 264 S.C. 573, 580, 216

S.E.2d 518, 521 (1975). Here, there is certainly mutuality of parties. Moreover, although

the provision of the motel accommodations may not have been directly encompassed within

the tcrms of the parties' agreement, the accommodations were provided in order to

facilitate Contractor's performance of the agreement. Also, as best we can discern, the

agreement between the parties concerning construction was not limited to the original

contract, but encompassed change orders and similar requests. The motel accommodations

could certainly be classified as part and parcel of the parties' entire agreement concerning

the renovations at the O.D. Cafe. Under these circumstances. the motel accommodations

were an appropriate subject for setoff.

p23


BRASINGTON TILE CO., INC. v. HAROLD G. WORLEY, et al.

B. ATTORNEYS, FEES TO PREVAILING PARTY

Contractor next argues that the special referee erred in determining Owner was the

prevailing party under section 29-5-10 for purposes of an award of attorneys' fees. We

disagree.

S.C. Code Ann. § 29-5-10(a) provides that the prevailing party to an action to

foreclose a mechanic's lien shall be awarded attorneys' fees and costs up to the amount of

the actual lien award. Subsection (b) of the statute specifies the method for determining

the prevailing party to the litigation:

Not less than fifteen days before the first term of court at which the

trial is set, either party may file and serve on the other party an offer of

settlement, and within ten days thereafter the party served may respond by

filing and serving his offer of settlement. The offer shall state that it is made

under this section and specify the amount, exclusive of interest and costs,

which the party serving the offer is willing to agree constitutes a settlement

of the lien. . . .

* * *

* * *

If a written offer of settlement is made by both parties, the party whose offer is closer to the verdict reached is considered the prevailing party in the action. If the difference between both offers and the verdict is equal,

neither party is considercd to be the prevailing party for purposes of

determining the award of costs and attorney's fees.

If the plaintiff makes no written offer of settlement, the amount

prayed for in his complaint is considered to be his final offer of settlement

for purposes of this section.

If the defendant makes no written offer of settlement, his offer of settlement is considered to be zero.

(emphasis added).

Contractor first argues that the word "verdict," as used in the statute, should be

construed to mean only the amount awarded on the mechanic's lien itself without regard

to any offsets. If this Court so construes "verdict," Contractor will be the prevailing party

in this action and thus will be entitled to attorneys' fees.

No South Carolina case directly addresses this issue as it relates to mechanic's liens.

However, the general rule concerning the effect of a setoff is that

p24


BRASINGTON TILE CO., INC. v. HAROLD G. WORLEY, et al.

a setoff . . . becomes part of a single controversy between the parties,

requiring only one verdict and one judgment according to the facts.

Generally, if an established setoff or counterclaim is less than the plaintiff's

demand, the plaintiff has judgment for the residue only.

20 Am. Jur. 2d Counterclaim, Recoupment, & Setoff § 88 (1995).

We find that this rule applies in the context of South Carolina's mechanic's lien

statutes where the party defending against the lien is entitled to offsets or has prosecuted

successfully a compulsory counterclaim. A mechanic's lien is intended to secure payment

for the value of "labor performed or furnished or for materials furnished and actually used

in the erection, alteration, or repair of a building or structure upon real estate . . . by

virtue of an agreement with . . . the owner of the building or structure . . . . " S.C. Code

Ann. § 29-5-10. The value of the labor performed is necessarily affected by the quality

of a contractor's workmanship, and the amount an owner owes a contractor for a project

is necessarily affected by amounts paid by the owner for which the contractor was actually

responsible. Setoffs and compulsory counterclaims, which are by definition closely related

to the underlying dispute about which the plaintiff filed a lawsuit, directly affect the

amount an owner actually owes for construction and are part of one verdict along with

amounts expended by a contractor for labor and materials.

Mechanic's liens statutes vary from state to state, and provisions concerning

attorneys' fee awards to prevailing parties vary widely. Nevertheless, some cases from

other jurisdictions provide valuable guidance on the question whether setoffs and

counterclaims should be considered in the determination of the prevailing party. In Ferrell v. Ashmore, 507 So. 2d 691 (Fla. Ct. App.. 1987), a contractor brought an action against

a homeowner for foreclosure of a mechanic's lien for costs incurred in constructing the

home. The homeowner filed a counterclaim against the contractor, alleging breach of the

construction contract. The trial court ultimately found that the contractor was entitled to

recover approximately $10,820 under his mechanic's lien claim and the homeowner was

entitled to approximately $31,000 on his counterclaim. The contractor then argued that

because the trial court had found him entitled to recover under the mechanic's lien statute,

he was the prevailing party and was, therefore, entitled to attorneys' fees.

The Florida District Court of Appeals disagreed. It concluded that "where the

owner's successful counterclaim, which is predicated upon a breach of the same contract

under which the contractor/lienor furnished its materials and labor, effectively defeats

enforcement of the contractor's otherwise valid mechanic's lien," the owner is the

prevailing party entitled to attorneys' fees. Id. at 695.

Similarly, in Moritzky v. Heberlein, 697 P.2d 1023 (Wash. Ct. App. 1985), a

p25


BRASINGTON TILE CO., INC. v. HAROLD G. WORLEY, et al.

contractor brought an action to foreclose a mechanic's lien on a house after the homeowner

refused to pay certain costs associated with construction. The homeowner's answer

contained a counterclaim against the contractor for negligent, incomplete work as well as

for certain code violations. The trial court foreclosed the mechanic's lien for the full

amount requested by the contractor, but ruled in favor of the homeowner on the

counterclaim, awarding more than twice the amount of the mechanic's lien. The court

then awarded attorneys' fees to the contractor, finding that the contractor was the

"prevailing party" in the action to foreclose the lien. The homeowner appealed the award

of attorneys' fees.

On appeal, the Washington Court of Appeals reversed the award of attorneys' fees

to the contractor. It reasoned that the claims brought by the homeowner were compulsory

counterclaims directly related to the underlying dispute and that the action "was tried as

one lawsuit." Id. at 1025. Under such circumstances, the "determination of which party

is the prevailing party, whether for the purpose of awarding costs or attorney fees, is made

on the basis of which party has an affirmative judgment rendered in his favor at the

conclusion of the entire case." Id. at 1024-25 (emphasis in original). See also, e.g., First General Servs. v. Perkins, 918 P.2d 480 (Utah Ct. App. 1996)(suggesting that

counterclaims that are closely related to the mechanic's lien claim can defeat a mechanic's

lien for purposes of award of attorneys' fees under the mechanic's lien statute).

Admittedly, these cases construe "prevailing party" statutes that differ from S.C.

Code Ann. § 29-5-10(b). Nevertheless, they stand for the common sense proposition that

where counterclaims and setoffs asserted in mechanic's lien actions are closely related to

the underlying controversy, the controversy is, in actuality, one controversy with one

judgment and one verdict. We agree with that proposition and conclude that the setoff

should be considered in determining the prevailing party.4


4 In Utilities Construction Co. v. Wilson, 321 S.C. 244, 247, 468 S.E.2d 1, 2 (Ct.

App. 1996), the Court of Appeals held that "it is the enforcement of the lien which confers

the right to attorneys' fees, and not the joinder of an attempted enforcement with another

non-statutory cause of action on which the lienor prevails. " Unlike the present case,

Utilities Construction involved a situation in which the plaintiff was found not to have a

valid lien at all, and under those circumstances, the Court of Appeals correctly concluded

the plaintiff could not be the prevailing party. Here, however, where there is some

entitlement to a mechanic's lien, it is entirely appropriate to consider compulsory

counterclaims, offsets, and other closely related joined claims in determining the amount

of the verdict. Determination of the prevailing party should be based on one verdict in the

action, assuming some entitlement to a mechanic's lien.

Moreover, the realities of settlement negotiation as well as the language of section

p26


BRASINGTON TILE CO., INC. v. HAROLD G. WORLEY, et al.

Finally, Contractor argues that for purposes of determining who is the prevailing

party, the value of Owner's counterclaim should be considered its "settlement offer."

Under such a theory, Owner's settlement offer would be approximately negative $24,000

(Owner's counterclaim was for $24,000), while Contractor's settlement offer would be

approximately $34,000, the amount it requested in the Complaint. The special referee

awarded $14,846.81, which is closer to $34,000 than to negative $24,000. Contractor

concludes that it is the prevailina party under this method and is entitled to attorneys' fees

and costs.

Contractor is correct that under the method it suggests it would be the prevailing

party. Unfortunately for Contractor, that method is not prescribed by the plain language

of section 29-5-10. As quoted above, section 29-5-10 provides that when neither party

makes a written offer of settlement, the plaintiff's offer is considered the amount prayed

for in its complaint and the defendant's offer is considered to be zero. Whether fairly or

unfairly, the statute does not make provision for considering counterclaims as negative

offers of settlement.

Here, the Record does not reflect that either party made a written offer of

settlement. The clear terms of the statute mandate, therefore, that Contractor's settlement

offer be the amount prayed for in the Complaint, $34,200.46, and Owner's settlement

offer be considered zero. The special referee ultimately awarded $14,846.81, which is

closer to zero than it is to $34,200.46. Using the formula prescribed in section 29-5-10,

Owner is the prevailing party and is entitled to attorneys' fees and costs in an amount no

greater than the value of the mechanic's lien award.

CONCLUSION

For the foregoing reasons, the decision of the special referee is AFFIRMED.

FINNEY, C.J., MOORE, and WALLER, JJ., and Acting Associate

Justice Marc H. Westbrook, concur.


29-5-10 dictate consideration of offsets and compulsory counterclaims. Section 29-5-10(b)

provides a formula for determining the prevailing party when the parties have made written

offers of settlement. If, in determining the "prevailing party," one considered only the

mechanic's lien cause of action, parties would be forced to make two settlement offers --

one for the mechanic's lien portion of the lawsuit and the other for the entire lawsuit. It

is implausible that the General Assembly actually intended such a result. Moreover, the

statute refers to "verdict" in the singular. Given that setoffs form part of one verdict with

the underlying claim, it makes sense to read the statute in such a way that compulsory

counterclaims and offsets are taken into account.

p27